Question: In a back-office system implementation project, the team is unable to plan in detail the development phase until all the design work is complete. Which
In a back-office system implementation project, the team is unable to plan in detail the development phase until all the design work is complete.
Which project management approach would BEST address the situation?
A. Rolling wave B. Contingency reserve C. Critical chain D. Float