Question: In a project that involves an adaptive life cycle, two processes are repeated for each iteration to confirm scope verification. What are the names of
In a project that involves an adaptive life cycle, two processes are repeated for each iteration to confirm scope verification. What are the names of the processes mentioned in the above scenario?
A. Validate Scope and Control Scope B. Control Quality and Validate Scope C. Define Scope and Validate Scope D. Direct and Manage Project Work and Validate Scope