Question: In performing cost estimating, activity cost estimates do not rely on which of the following inputs: a. Labor b. Material c. Equipment d. Requested changes
In performing cost estimating, activity cost estimates do not rely on which of the following inputs:
a. Labor
b. Material
c. Equipment
d. Requested changes