Question: Requested changes to cost estimating are processed for review and disposition through: a. Project management plan processes b. Cost management plan processes c. Integrated change

Requested changes to cost estimating are processed for review and disposition through:

a. Project management plan processes

b. Cost management plan processes

c. Integrated change control processes

d. Risk management plan processes