Question: In respect to SCRUM Risk, When the . . . . . . . . . . . . . . . . . .
In respect to SCRUM Risk, When the . . . . . . . . . . . . . . . . . . . . . Risks are identified, the . . . . . . . . . . . . . . . . . . . . . Product Owner must assess the Probability and Impact of each Risk; prioritize these Risks; and determine the right Responses.
The . . . . . . . . . . . . . . . . . . . . . Product Owner must communicate these Risks to the relevant Stakeholders, Program’s Teams, and Projects’
Teams.
A) Portfolio/Portfolio/Portfolio B) Program/Program/Program C) Project/Project/Project D) All Options above are Incorrect.
ANSWER: A