Question: In respect to SCRUM Risk, a . . . . . . . . . . . . . . . . . . .
In respect to SCRUM Risk, a . . . . . . . . . . . . . . . . . . . . . . . . . . is responsible for helping in identifying and escalating the Project potential Risks to the Scrum Team.
A) Product Owner B) Scrum Master C) Scrum Team D) Stakeholders ANSWER: B