Question: Parametric estimating is used in: A. Estimating the resources for an activity B. Assessing the duration for an activity C. Sequencing the schedule activities D.
Parametric estimating is used in:
A. Estimating the resources for an activity B. Assessing the duration for an activity C. Sequencing the schedule activities D. Controlling the schedule