Question: The . . . . . . . . . . . . . . . . . . . . . . Approach is
The . . . . . . . . . . . . . . . . . . . . . . Approach is designed to deal with the Uncertainties in Managing Projects such as having limited Availability of the needed Human Resources and/or Physical Resources. Constrained Tasks and Activities are given Higher Priorities during the Project Planning, Resource Allocation, and Execution.
A) Critical-Chain-Based Project Management (CCBPM)
B) Critical-Chain-Based Project Planning (CCBPP)
C) Critical-Chain-Based Project Execution (CCBPE)
D) Critical-Chain-Based Project Manager ANSWER: A