Question: The Change Control Board has approved a change request for performing corrective action. What is the NEXT step? A. Implementing the change. B. Updating the

The Change Control Board has approved a change request for performing corrective action.

What is the NEXT step?

A. Implementing the change.

B. Updating the Change Log.

C. Updating the Project Management Plan. D. Analyzing the impact of the change.