Question: The document that formally authorizes the project has been created and approved. A new project manager has been appointed, and a list of key stakeholders
The document that formally authorizes the project has been created and approved. A new project manager has been appointed, and a list of key stakeholders has also been identified as a part of the process.
What should be done NEXT?
A. The newly appointed project manager should hold a kick-off meeting.
B. The newly appointed project manager should start the preparation of developing a project management plan with the available list of key stakeholders.
C. The newly appointed project manager should update the business case and build a new implementation strategy.
D. Information on the approved project charter should be shared with stakeholders to ensure a common understanding of the key deliverables, milestones, and their roles and responsibilities.