Question: The main Inputs to the Estimate Activity Resources Process include the following: A) The Project Management Plan along with its subsidiary Plans, which are the

The main Inputs to the “Estimate Activity Resources” Process include the following:

A) The Project Management Plan along with its subsidiary Plans, which are the resource management plan, and the scope baseline.

B) The Project Management Plan along with its subsidiary Project Documents, which are the activity attributes, activity list, assumption log, cost estimates, resource calendars, and risk register.

C) Both Options above are Correct.

D) All Options above are Incorrect.

ANSWER: C

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management For Small Projects Questions!