Question: The main Inputs to the Estimate Activity Resources Process include the following: A) The Project Management Plan along with its subsidiary Plans, which are the
The main Inputs to the “Estimate Activity Resources” Process include the following:
A) The Project Management Plan along with its subsidiary Plans, which are the resource management plan, and the scope baseline.
B) The Project Management Plan along with its subsidiary Project Documents, which are the activity attributes, activity list, assumption log, cost estimates, resource calendars, and risk register.
C) Both Options above are Correct.
D) All Options above are Incorrect.
ANSWER: C