Question: The main Inputs to the Estimate Tasks Process include the following: A) Inputs from the Scrum Team and the Scrum Guidance Body (SGB). B) The
The main Inputs to the “Estimate Tasks” Process include the following:
A) Inputs from the Scrum Team and the Scrum Guidance Body (SGB).
B) The list of the created Tasks, the list of identified Risks, and the list of identified Dependencies among the created Tasks.
C) The User-Stories Acceptance-Criteria.
D) All Options above are Correct.
ANSWER: D