Question: The main Inputs to the Identify Stakeholders Process include the Project Charter, the Business Case Document, the Benefits Management Plan, the Communications Management Plan, the

The main Inputs to the “Identify Stakeholders” Process include the Project Charter, the Business Case Document, the Benefits Management Plan, the Communications Management Plan, the Stakeholders Engagement Plan, the Change Log, the Issue Log, the Requirements Documentation, and the Project Agreements.

A) _TRUE_ B) _FALSE_ ANSWER: A