Question: The main Inputs to the Validate Scope Process include the Project Management Plan and its subsidiaries, a set of the Project Documents, the set of
The main Inputs to the “Validate Scope” Process include the Project Management Plan and its subsidiaries, a set of the Project Documents, the set of Verified Deliverables, and the Work Performance Data/Information/Reports.
A) _TRUE_ B) _FALSE_ ANSWER: A