Question: The main Inputs to the Define Scope Process include the following: A) The Project Charter and the Project Management Plan along with its subsidiary Plans

The main Inputs to the “Define Scope” Process include the following:

A) The Project Charter and the Project Management Plan along with its subsidiary Plans and Project document, B) The Project Charter along with all of the Project Agreements.

C) A set of relevant Organizational Process Assets and a set of relevant Enterprise Environmental Factors.

D) All Options above are Correct.

ANSWER: D