Question: The main Outputs of the Develop Schedule Process include the following: A) The Schedule Baseline, the Schedule Data, and the Project Schedule. B) The Project

The main Outputs of the “Develop Schedule” Process include the following:

A) The Schedule Baseline, the Schedule Data, and the Project Schedule.

B) The Project Calendars and the set of Change Requests.

C) Updated versions of the Schedule Management Plan, the Activity Attributes, the Assumption Log, the Duration Estimates, the Lessons Learned Register, the Resource Requirements, and the Risk Register.

D) All Options above are Correct.

ANSWER: D