Question: The Perform Integrated Change Control Process is to manage and review all CHANGE-REQUESTS and approve and implement some of them. A) _TRUE_ B) _FALSE_ ANSWER:

The “Perform Integrated Change Control” Process is to manage and review all CHANGE-REQUESTS and approve and implement some of them.

A) _TRUE_ B) _FALSE_ ANSWER: A