Question: The project manager has just been informed that one stakeholder is unhappy about a specific deliverable. The project manager believes that the stakeholders concern should

The project manager has just been informed that one stakeholder is unhappy about a specific deliverable. The project manager believes that the stakeholder’s concern should not be an issue because the deliverable will fully address the need. What should the project manager do?

A. Inform management.

B. Send the requirements documentation to the stakeholder to prove that the adopted scope meets the need.

C. Set up a meeting with the stakeholder to discuss his concerns.

D. Ask the stakeholder to clearly document his requirement and issue a change request.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management For Small Projects Questions!