Question: The project manager has just completed a high-level risk identification. What should be done NEXT? A. Perform a qualitative risk analysis. B. Plan risk responses.

The project manager has just completed a high-level risk identification.

What should be done NEXT?

A. Perform a qualitative risk analysis.

B. Plan risk responses.

C. Identify detailed risks.

D. Develop the project management plan.