Question: The Project Resource Management Knowledge Area includes six processes that are necessary to (i) identify, acquire, and manage Resources; and (ii) ensure that the right
The Project Resource Management Knowledge Area includes six processes that are necessary to (i) identify, acquire, and manage Resources; and (ii) ensure that the right Resources will be available at the right time and place. These Processes are the “Plan Resource Management” Process, the “Estimate Activity Resource” Process, the “Acquire Resources” Process, the “Develop Team” Process, the “Manage Team” Process, and the “Control Resources” Process.
A) _TRUE_ B) _FALSE_ ANSWER: A