Question: Two weeks before the scheduled finish date, your project still has a significant number of open product defects. You want to focus the defect repair
Two weeks before the scheduled finish date, your project still has a significant number of open product defects. You want to focus the defect repair effort on the more frequent defects. Which tool should you use?
A. Pareto diagram B. Cause-and-effect diagrams C. Cost of quality D. Sampling