Question: Using the' list of activity dependencies given below, draw an accurate and economical (minimizing the use of dummies) network. Activity Depends on Activity A none

Using the' list of activity dependencies given below, draw an accurate and economical (minimizing the use of dummies) network.

Activity Depends on Activity A none B -A F A H A C B D 8 E C Activity Depends on Activity G F I F J H K I and J L G, D, andE M K N L and M