Question: What are the key inputs to the identify stakeholders process? A. Project charter, organizational chart, stakeholder analysis, organizational process assets B. Vendor requirements, project statement
What are the key inputs to the identify stakeholders process?
A. Project charter, organizational chart, stakeholder analysis, organizational process assets B. Vendor requirements, project statement of work, enterprise environmental factors C. Project charter, project statement of work, approved change requests, organizational process assets D. Project charter, business case, communications management plan, stakeholder management plan, project documents