Question: What information and method would be best to use when presenting a detailed project update to some high-level stakeholders? A. A verbal presentation during a
What information and method would be best to use when presenting a detailed project update to some high-level stakeholders?
A. A verbal presentation during a 10-minute meeting B. A summary milestone report tabled as an agenda item at their next scheduled meeting C. A PowerPoint presentation outlining the major issues given in your office D. A detailed performance report in writing with an accompanying presentation and time for questions and answers