What is the correct order of project activities?

A. Develop project management plan, execute project, develop project charter, conduct project selection B. Conduct project selection, develop project charter, execute project, develop project management plan C. Conduct project selection, develop project charter, develop project management plan, execute project D. Develop project charter, develop project management plan, execute project, conduct project selection