Question: PREPARE a comprehensive and effective Work Breakdown Structure for the British Columbia Roads in tree diagram WBS template. - Project: Reconnecting British Columbia Roads After

PREPARE a comprehensive and effective Work Breakdown Structure for the British Columbia Roads in tree diagram WBS template.

- Project: Reconnecting British Columbia Roads After Massive Flooding

- 1.1 Project Initiation

- 1.1.1 Define Project Objectives

- 1.1.2 Establish Project Team

- 1.1.3 Identify Stakeholders

- 1.1.4 Develop Project Charter

- 1.2 Project Planning

- 1.2.1 Develop Project Management Plan

- 1.2.2 Identify Critical Roads

- 1.2.3 Risk Assessment and Management Plan

- 1.2.4 Resource Allocation

- 1.2.5 Budget Planning

- 1.3 Highway Selection

- 1.3.1 Select Highway 5 (Coquihalla Highway) as Priority

- 1.3.2 Assess Highway 1 and Other Routes

- 1.4 Damage Assessment

- 1.4.1 Aerial Survey of Damage

- 1.4.2 Site Identification

- 1.4.3 Data Collection and Documentation

- 1.4.4 Environmental Impact Assessment

- 2. Highway 5 Restoration

- 2.1 Site Preparation

- 2.1.1 Clear Debris from Access Points

- 2.1.2 Establish Temporary Work Camps

- 2.1.3 Secure Equipment and Materials

- 2.2 Debris Removal and Cleanup

- 2.2.1 Debris Removal at Specific Sites

- 2.2.2 Clearance of Landslides and Blockages

- 2.2.3 Environmental Remediation

- 2.3 Structural Repairs

- 2.3.1 Bridge Inspections and Repairs

- 2.3.2 Culvert Restoration

- 2.3.3 Road Surface Repairs

- 2.3.4 Guardrail Installation

- 2.4 Material Procurement

- 2.4.1 Rock and Asphalt Procurement

- 2.4.2 Stockpiling of Materials

- 2.4.3 Material Quality Control

- 2.5 Construction and Roadwork

- 2.5.1 Mobilization of Construction Crews

- 2.5.2 Pavement Rehabilitation

- 2.5.3 Drainage Improvements

- 2.5.4 Signage Installation

- 2.6 Quality Assurance

- 2.6.1 Quality Inspections and Testing

- 2.6.2 Compliance with Engineering Standards

- 2.7 Safety Measures

- 2.7.1 Worker Safety Training

- 2.7.2 Safety Inspections

- 2.7.3 Emergency Response Planning

- 2.8 Weather-Related Challenges

- 2.8.1 Monitoring Weather Conditions

- 2.8.2 Snow Removal and Management

- 2.8.3 Adaptations for Extreme Cold

- 3. Stakeholder Engagement

- 3.1 Community Outreach

- 3.1.1 Public Information Campaigns

- 3.1.2 Community Meetings

- 3.1.3 Addressing Concerns and Feedback

- 3.2 Government and Partner Collaboration

- 3.2.1 Coordination with Local Authorities

- 3.2.2 Collaboration with Contractors

- 3.2.3 Engaging Volunteer Organizations

- 3.3 Communication Protocols

- 3.3.1 Daily Briefings

- 3.3.2 Executive Sponsor Updates

- 3.3.3 Reporting to Government Leaders

- 4. Project Monitoring and Control

- 4.1 Progress Tracking

- 4.1.1 Schedule Adherence

- 4.1.2 Budget Monitoring

- 4.1.3 Quality Control Checks

- 4.2 Risk Management

- 4.2.1 Risk Assessment Updates

- 4.2.2 Risk Response Plan Adjustments

- 4.3 Change Management

- 4.3.1 Scope Changes and Approval

- 4.3.2 Documenting Change Requests

- 5. Project Closure

- 5.1 Completion and Handover

- 5.1.1 Final Inspections

- 5.1.2 Documentation and Record-Keeping

- 5.1.3 Handover to Transportation Authorities

- 5.2 Lessons Learned

- 5.2.1 Post-Project Evaluation

- 5.2.2 Documentation of Best Practices

- 5.2.3 Knowledge Transfer

- 6. Documentation and Reporting

- 6.1 Project Documentation

- 6.1.1 Data Collection and Storage

- 6.1.2 Document Control

- 6.2 Reporting

- 6.2.1 Progress Reports

- 6.2.2 Stakeholder Updates

- 6.2.3 Government and Executive Reporting

PLEASE CREATE IT IN TREE DIAGRAM TEMPLATE ONLY. CHECK THE TREE WBS TEMPLATE BEFORE ANSWERING.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!