Question: What two outputs are created in the Develop Project Charter process? A. Project charter and constraint list B. Project charter and business documents C. Project

What two outputs are created in the Develop Project Charter process?

A. Project charter and constraint list B. Project charter and business documents C. Project charter and organizational process assets D. Project charter and assumption log