Question: Which project management processes in the Executing process group provide change requests as an input to the Perform Integrated Change Control process? A. Direct and
Which project management processes in the Executing process group provide change requests as an input to the Perform Integrated Change Control process?
A. Direct and Manage Project Execution, Schedule Control B. Manage Quality, Project Contract Administration C. Direct and Manage Project Work, Perform Quality Control D. Implement Risk Responses, Manage Quality, Direct and Manage Project Work