Question: You are managing a project in biotechnology code named Mitochondria Eve. You need performance measurements to write the performance reports.Which process(es) will you run? A.

You are managing a project in biotechnology code named Mitochondria Eve. You need performance measurements to write the performance reports.Which process(es)

will you run?

A. Report Performance B. Control Scope, Control Schedule, and Control Cost C. Control Scope and Perform Quality Control D. Monitor and Control Project Work