Question: You are managing a project in biotechnology code named Mitochondria Eve. You need work performance measurements or information to write the performance reports. Which process(es)
You are managing a project in biotechnology code named Mitochondria Eve. You need work performance measurements or information to write the performance reports.
Which process(es) will you run?
A. Monitor and Control Project Work B. Control Scope, Control Schedule, and Control Cost C. Develop Project Work Performance Report D. Direct and Manage Project Work