Question: You are managing a project to set up data servers to support a website for an enterprise customer. The location for the servers has been
You are managing a project to set up data servers to support a website for an enterprise customer. The location for the servers has been placed close to the customer due to their requirements. However, this location is prone to natural disasters, such as hurricanes and flooding.
You have decided to install some extra servers in another city that will act as backup if a disaster happens.
This is an example of which of the following?
A. Risk avoidance B. Risk mitigation C. Risk acceptance D. Risk transfer
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts