Question: You are preparing to develop the WBS for the Singular Intelligence project.Which of the following is a true statement about the WBS? A. It is

You are preparing to develop the WBS for the Singular Intelligence project.Which of the following is a true statement about the WBS?

A. It is a deliverable-oriented hierarchical decomposition of the project work to be performed by the project team.

B. It’s a hierarchically organized set of resources needed by the project.

C. It’s a hierarchically organized set of risks identified for the project.

D. It represents the reporting hierarchy in the performing organization.