Question: You are the project manager for a project with the following network diagram. Study the following diagram: Which path is the critical path? A. ABCD
You are the project manager for a project with the following network diagram. Study the following diagram: Which path is the critical path?

A.
ABCD B.
EBCD C.
EFH D.
EGH
Start 4 5 S E B 4 FL G H End