Question: You are the project manager for a technical implementation project. The customer has requested that you factor in the after-the-project costs, such as maintenance and
You are the project manager for a technical implementation project. The customer has requested that you factor in the after-the-project costs, such as maintenance and service. This is an example of which one of the following?
A. Life-cycle costs B. Scope creep C. Project spin-off D. Operations