Question: You have been appointed project manager for a project that is already executing. The previous project manager handed you the risk register. Which of the

You have been appointed project manager for a project that is already executing. The previous project manager handed you the risk register. Which of the following do you not expect to see in this document?

A. List of identified risks 

B. Risk probability and impact matrix 

C. List of potential responses 

D. Root causes of risks