Question: You have created the work performance report about the project that you are managing. Which process will you use to distribute the report among the
You have created the work performance report about the project that you are managing. Which process will you use to distribute the report among the stakeholders?
A. Manage Stakeholders B. Distribute Reports C. Distribute Information D. Manage Communication