Question: You have created the performance report about the project that you are managing. Which process will you use to distribute the report among the stakeholders?
You have created the performance report about the project that you are managing.
Which process will you use to distribute the report among the stakeholders?
A. Report Performance B. Distribute Reports C. Distribute Information D. Manage Stakeholder Expectations