Question: You have issued a change request, and because it requires corrective action beyond your approval level, your next step is to: A. Schedule a meeting
You have issued a change request, and because it requires corrective action beyond your approval level, your next step is to:
A. Schedule a meeting with your PMO B. Receive governance approval to proceed C. Set up a change control board to see if the change should be implemented D. Use your project management information system (PMIS)