Question: Which process group or process provides the most primary interface with the project governance structure? A. Executing B. Monitoring and Controlling C. Direct and Manage
Which process group or process provides the most primary interface with the project governance structure?
A. Executing B. Monitoring and Controlling C. Direct and Manage Project Work D. Monitor and Control Project Work