Question: You know from a network diagram that Activity B cannot start until Activity A is finished. Which of the following are true? A. Activities A

You know from a network diagram that Activity B cannot start until Activity A is finished. Which of the following are true?

A. Activities A and B have a start-to-finish dependency.

B. Activities A and B have a finish-to-start dependency.

C. Activity B has a mandatory dependency on Activity A.

D. Activities A and B are on a critical path.