You know from a network diagram that Activity B cannot start until Activity A is finished. Which of the following are true?
A. Activities A and B have a start-to-finish dependency.
B. Activities A and B have a finish-to-start dependency.
C. Activity B has a mandatory dependency on Activity A.
D. Activities A and B are on a critical path.