Consider the project information given in Table 17. a. Calculate the project cost based just on the

Question:

Consider the project information given in Table 17. 

TABLE 17 Activity A B C D E F Immediate predecessors A A C, B B Expected time (weeks) 362713 Normal cost ($)

a. Calculate the project cost based just on the costs of the activities. 

b. Generate the weekly and cumulative cash flow charts, once for an early-start schedule and once for a late-start schedule. 

c. Discuss the implications of the charts generated in part (b).