Question: 112. Bob is a project manager in a functional organization. He disagrees with the project sponsor on how some activities of the project should commence.

112. Bob is a project manager in a functional organization. He disagrees with the project sponsor on how some activities of the project should commence. The project sponsor, however, insists that Bob have the project team begin working on the project. What should Bob do?

A. Instruct the project team to begin working on the project.

B. Object to the project sponsor’s manager.

C. Document the disagreements in a formal report for lessons learned when the project fails.

D. Instruct the project team to work only on critical path activities.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management The Managerial Process Questions!