Question: 28. Your project is complete. It was the first project in your company to use the agile approach. The deliverables were identified by the product
28. Your project is complete. It was the first project in your company to use the agile approach. The deliverables were identified by the product owner. Some of the stakeholders are concerned about quality and have not signed off on the deliverables. The best way to collect feedback on the definition of “done” is to:
A. Create a wiki site for five days so stakeholders can provide their comments anonymously B. Go back and look at all the lessons learned to evaluate strategic alignment C. Set up a focus group after you send out a satisfaction survey D. Conduct a product review meeting with the concerned stakeholders