Question: 3. You are developing the project charter for a project for an external customer. To complete the project charter, which of the following should be
3. You are developing the project charter for a project for an external customer. To complete the project charter, which of the following should be in place?
A. The detailed features list to be delivered B. The not-to-exceed price for the project C. The agreed-upon contract for the project D. The estimated labor costs of the project