Question: 3. You are the project manager for a small project team for a project that has a set of approved functional requirements. In one of
3. You are the project manager for a small project team for a project that has a set of approved functional requirements. In one of the regular meetings, your software developer team member, Patty, proposes an additional feature to the system. As project manager, you remind the team that they must concentrate on completing only the work approved. Your statement was guided by your adherence to:
A. Quality management B. Change management C. Scope management D. Configuration management