Question: You are the project manager for a small project team. In one of the regular meetings, a team member proposes an additional feature to the

You are the project manager for a small project team. In one of the regular meetings, a team member proposes an additional feature to the system you are developing. As project manager, you remind the team that they must concentrate on completing only the work approved. Which knowledge area is this an example of?

A. Project Quality Management

B. Project Change Management

C. Project Scope Management

D. Project Configuration Management