Question: 60. A major educational institution is late in developing a project that allows students to attend classes and complete educational requirements online. This has resulted

60. A major educational institution is late in developing a project that allows students to attend classes and complete educational requirements online. This has resulted in a 20% reduction in enrollment and led the executive board to establish a project that will increase enrollment in the next year by 10%. Part of your project is delayed pending availability of resources. The programming can start in the next two weeks. The delayed projects will maintain the staff, regardless of changes, because no other resources are available and the budget does not support hiring contractors who have the necessary expertise. Which of the following will be least useful in developing the teams for these projects under these conditions?

A. Training plan B. Staffing management plan C. Project preferred-vendor list D. Training records

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management The Managerial Process Questions!