Question: 95. If the CPI is expected to be the same for the remainder of the project, you should calculate the projects estimate at completion (EAC)
95. If the CPI is expected to be the same for the remainder of the project, you should calculate the project’s estimate at completion (EAC) by using the following formula:
A. AC + ETC B. BAC / CPI C. AC + (Remaining PV / CPI)
D. AC + BAC − EV
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
