Question: 95. If the CPI is expected to be the same for the remainder of the project, you should calculate the projects estimate at completion (EAC)

95. If the CPI is expected to be the same for the remainder of the project, you should calculate the project’s estimate at completion (EAC) by using the following formula:

A. AC + ETC B. BAC / CPI C. AC + (Remaining PV / CPI)

D. AC + BAC − EV