Question: Beth is the project manager of a software development project. She and her project team are done with a phase and Beth needs to make
Beth is the project manager of a software development project. She and her project team are done with a phase and Beth needs to make certain the lessons-learned documentation is complete before moving the project onto the next phase. On any project, the lessons-learned document is created by which of the following?
A. The customers B. The project sponsor C. The project team D. The stakeholders