Question: In which process is the project schedule created? a) Define Activities b) Sequence Activities c) Develop Schedule d) Estimate Activity Durations
In which process is the project schedule created?
a) Define Activities
b) Sequence Activities
c) Develop Schedule
d) Estimate Activity Durations